When will the second facility of Viet Duc Hospital and Bach Mai Hospital be operational?

Báo Xây dựngBáo Xây dựng20/12/2024


On the afternoon of December 20th, at a press conference, Mr. Le Duc Luan, Deputy Minister of Health, provided information on the progress of the construction of the second facilities for Viet Duc and Bach Mai hospitals.

Currently, in terms of construction, the second facility of Bach Mai Hospital is 97% complete, with 3% remaining; the second facility of Viet Duc Hospital is also 85% complete, with only 15% remaining... Since construction was temporarily halted in 2020, the Viet Duc Hospital project has now resumed construction.

Cơ sở 2 của Bệnh viện Việt Đức và Bệnh viện Bạch Mai khi nào hoạt động?- Ảnh 1.

The second facility of Bach Mai Hospital is currently under construction. (Photo: PT).

Mr. Luan stated that the complex obstacles relate to the contract implementation process, contract signing, and project deployment, with some aspects not complying with regulations in decrees and circulars. Therefore, through the review process, the Ministry of Health proposed to the Government, based on these obstacles, to develop specific mechanisms and policies to resolve the difficulties and obstacles. Only by applying these mechanisms and policies can the difficulties and obstacles be overcome and the project continue to be implemented.

According to Deputy Minister Le Duc Luan, the Ministry of Health is coordinating with other ministries and agencies to finalize the content related to the Government 's Resolution to address this issue. After resolving these difficulties and obstacles, the projects will be accelerated.

Besides the construction progress reaching nearly 100%, regarding medical equipment, according to Mr. Luan, "for medical equipment projects approved in 2014-2015, we will review and compare the implementation with the actual situation and organize the procurement of medical equipment, each project worth nearly 1,000 billion VND. The goal is that if the difficulties and obstacles are accepted by the competent authorities, we will complete the construction in 2025."

Regarding the second facilities of these two hospitals, in November 2024, the Prime Minister requested that within six months, the Ministry of Health must complete and hand over the two second facilities for operation.



Source: https://www.baogiaothong.vn/co-so-2-cua-benh-vien-viet-duc-va-benh-vien-bach-mai-khi-nao-hoat-dong-1922412201652231.htm

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product