The project is constructed by the joint venture of Dacinco Construction Investment Company Limited - Nhat Huy Construction and Trading Company Limited, expected to be completed in May 2027.
Accordingly, the above open canal is replaced by a box culvert with a length of 420.49m, including manholes, wastewater separation wells, culvert sections across bridges and culvert sections connecting to Trung Nghia Lake.
The sluice gate at the beginning of the sewer line (at the existing separation well near Ton Duc Thang Street) was moved to the end of the sewer line (Trung Nghia Lake location) to prevent lake water from flowing into the wastewater collection system and install an automatic or manual opening and closing system.
Two routes, Hong Thai and Tan Trao, from Ton Duc Thang to Nguyen Tuong Pho, were upgraded, the roadway was widened from 5.5m to 7.5m; sidewalks were renovated, curbs were placed on both sides...
Above the culvert, a park and green trees have been invested in, synchronized with the landscaped green park that has been invested in the area between Yen The - Bac Son road (upstream), including: yard, walking path, badminton court, children's playground, flower beds, seats, huts, public toilets, exercise equipment, lighting system, trees and water supply system...
Source: https://baodanang.vn/cong-trinh-day-kin-kenh-ho-giua-2-duong-hong-thai-tan-trao-duoc-trien-khai-thi-cong-3306429.html