The 4.8 trillion VND project to build a road connecting Tan Son Nhat Airport in Ho Chi Minh City is entering its final phase, aiming for completion before the April 30th holiday as the land acquisition bottleneck has been completely resolved.
The Tran Quoc Hoan - Cong Hoa connecting road project commenced in late 2022, with a total investment of over 4,800 billion VND. The main road is over 4km long, 25-48m wide with 6 lanes, and connects to two additional branches, 18E and C2, which are 3-4 lanes wide.
In addition to the overpass in front of Terminal 3 at Tan Son Nhat Airport, the project also includes two underpasses at the major intersections of Tran Quoc Hoan - Phan Thuc Duyet and Truong Chinh - Tan Ky Tan Quy.
The project was expected to be operational by the end of 2024, but difficulties with land clearance have caused delays.


Speaking with a VietNamNet reporter, Mr. Le Huu Tuan, Deputy Head of the Compensation and Land Clearance Board of Tan Binh District (Ho Chi Minh City), said that all land-related obstacles have now been resolved.
"Today, the last house located in the alley off Tran Van Du Street will be completely demolished and handed over to the investor," Mr. Tuan informed.
Meanwhile, Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Traffic Works Management Board (the investor) confirmed that after receiving the land from Binh Tan district, the contractors will accelerate the construction progress to ensure the entire route is open to traffic before the April 30th holiday.



![]() | ![]() |




Besides accelerating the construction progress of the Tran Quoc Hoan - Cong Hoa connecting road, the investor is currently requesting the Tan Binh District People's Committee to urgently complete the A41 canal renovation project. This is an important project that will help connect the project's drainage system, ensuring the drainage capacity for the Tan Son Nhat airport area and Terminal 3, preventing flooding.
Two traffic projects aimed at alleviating congestion at Tan Son Nhat Airport have been opened to traffic.
The over 4.8 trillion VND road connecting Tan Son Nhat Airport is still facing obstacles due to 22 land acquisition issues.
Construction of Tan Son Nhat Airport Terminal 3 to be completed within the next 90 days.