Bien Hoa - Vung Tau Expressway section through Ho Chi Minh City and Dong Nai has been connected.

Bien Hoa - Vung Tau Expressway accelerates to the finish line: the Ho Chi Minh City - Dong Nai section has been connected, component project 3 has reached 97%. When completed, the entire route will reduce the load on National Highway 51, providing convenient connection from Ho Chi Minh City - Dong Nai to Long Thanh airport and Cai Mep - Thi Vai port cluster.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng05/12/2025

Bien Hoa - Vung Tau Expressway section through Ho Chi Minh City and Dong Nai has been connected.
Bien Hoa - Vung Tau Expressway section through Ho Chi Minh City and Dong Nai has been connected.

On December 5, Mr. Nguyen Cong Danh, Deputy Director of the Regional Traffic Project Management Board and the Agricultural Sector of Ba Ria - Vung Tau (Investor of the Bien Hoa - Vung Tau Expressway Component 3 project) said that the Bien Hoa - Vung Tau Expressway section through Ho Chi Minh City and Dong Nai has been connected, creating a premise for the entire project to be completed and put into operation soon.

The Bien Hoa - Vung Tau Expressway component project, phase 1 (the section through Ba Ria - Vung Tau previously) is entering the final stage, with construction output reaching more than 97% and the target of complete completion in December 2025.

z7294258678604_3b2b81dc721846ef2346a5a1dc0919dd.jpg
Bien Hoa - Vung Tau Expressway connects Ho Chi Minh City - Dong Nai

This is one of the key transport projects that the Government has requested to accelerate progress, in order to soon put the expressway connecting the Southeast region into synchronous operation.

With a length of 19.5km and a total investment of more than VND 7,216 billion, component project 3 was technically opened to traffic on April 19, 2025, becoming a strategically important route in the East of Ho Chi Minh City. The route not only opens the way to the Cai Mep - Thi Vai port cluster but also plays a connecting role between Bien Hoa and Ba Ria.

Currently, the main road of the project has completed the asphalt concrete surface, the paint system, the median strip and the protective fence. The construction teams are focusing on the lighting system, traffic safety, and completing the traffic organization at the Hoi Bai - Phuoc Tan intersection and National Highway 56.

According to the Regional Traffic Project Management Board and the Agricultural Sector of Ba Ria - Vung Tau, the site clearance for the main area has been 100% completed. The additional areas in Tam Long ward, Tan Thanh ward, Chau Pha commune and the My Xuan - Ngai Giao intersection are being urgently inventoried by the localities, and compensation plans are being drawn up to hand over the site as soon as possible.

The bridge system on the route is also approaching the finish line. All 4 main bridges have been completed. Of the 7 overpasses, 5 have been completed; 2 bridges at Km42+167 and Km46+504 are being accelerated in terms of bridge deck and bridgehead construction to be completed in December 2025. The feeder roads have reached more than 95% of the volume.

The project progress (excluding the additional intersection and overpass) ensures completion of site work before December 15. The progress of the remaining project items ensures completion before December 31.

z7123489201482_a421d2e7513e5539521f03aedc62af8d.jpg
Component 3 project of Bien Hoa - Vung Tau Expressway reaches 97% progress

The important highlight is that the project component 3 has been technically opened to traffic since April, helping to create an "open road" for the project component 2 through Dong Nai (currently reaching more than 70% of output) to be able to connect. From Long Thanh area to the border of Ho Chi Minh City, the expressway has basically been connected, waiting for the completion of the last meters of asphalt on the section through Dong Nai to form a continuous axis from Bien Hoa to Ba Ria area.

Source: https://www.sggp.org.vn/cao-toc-bien-hoa-vung-tau-doan-qua-tphcm-va-dong-nai-da-noi-mach-post827025.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Notre Dame Cathedral in Ho Chi Minh City is brightly lit to welcome Christmas 2025
Hanoi girls "dress up" beautifully for Christmas season
Brightened after the storm and flood, the Tet chrysanthemum village in Gia Lai hopes there will be no power outages to save the plants.
The capital of yellow apricot in the Central region suffered heavy losses after double natural disasters

Same author

Heritage

Figure

Enterprise

Dalat coffee shop sees 300% increase in customers because owner plays 'martial arts movie' role

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC