The summary shows that site clearance work in some areas still exists and has not been completely resolved. In addition, the construction progress of some contractors is still slow, seriously affecting the goal of completing the entire project in 2025.
To end the delay and ensure strictness in direction and management, the Chairman of the Provincial People's Committee requests the Provincial Land Fund Development Center and the People's Committees of Tan Tien, Ea Knuec, and Ea Ning communes, according to their functions and tasks, to give maximum priority to human resources to coordinate, guide, and immediately resolve land-related procedures, such as: Verifying land origin for the remaining cases, approving specific land prices, compensation plans, support, resettlement, compensation, site clearance, etc., ensuring that no further delays arise. Take full responsibility before the Chairman of the Provincial People's Committee for the delay in site clearance work.
![]() |
Installation of booms of the traffic safety sign system of Component Project 3. |
For problems in Package 03 (Ea Knuec and Ea Ning communes): Complete the handover of all remaining sites, especially at the intersection of Provincial Road 10 and Tan Lap bridge area and other related locations, by the final deadline, before October 25, 2025.
For Tan Tien commune, it is required to urgently complete the approval of compensation plans, additional support for households in the area of People's Bridge 4 and the remaining resettlement procedures, the deadline for completion and transfer of documents to the Provincial Land Fund Development Center is before October 20, 2025.
For the Provincial Management Board of Investment Projects for Construction of Traffic Works and Rural Development Agriculture (investor), assign staff to closely monitor and work directly with localities and the Provincial Land Fund Development Center every day to urge and remove obstacles, ensuring progress milestones. Correct and handle contractors citing reasons for site clearance to delay construction and violating progress on the handed-over areas (if any). Urge contractors to concentrate maximum resources, complete the construction of the Provincial Road 10 intersection within the area where the site is available before October 20, 2025 and have a specific written commitment on the construction plan to compensate for the delayed output.
Source: https://baodaklak.vn/kinh-te/202510/giai-quyet-dut-diem-cac-vuong-mac-ve-mat-bang-du-an-thanh-phan-3-30c1724/