Long Thanh Airport before "D-Day": The plan to welcome the Boeing 787 superjumbo jet is complete.

VTV.vn - From air traffic control towers to runway systems, all technical processes have been activated at the highest level, ready for the first flights.

Đài truyền hình Việt NamĐài truyền hình Việt Nam12/12/2025

Sân bay Long Thành trước

The air traffic control tower at Long Thanh Airport is nearing completion. Photo: VATM

Air traffic infrastructure: The "brain" is ready.

According to updates as of mid-December, the Vietnam Air Traffic Management Corporation (VATM) has officially completed 100% of the preparations regarding infrastructure, equipment, and personnel. This is a crucial step in preparing for the series of technical flights scheduled to take place from December 15th to 19th.

Sân bay Long Thành trước

VATM has completed the construction and installation of the Long Thanh DVOR/DME navigation station.

Sân bay Long Thành trước

VATM has completed the installation of the Long Thanh primary and secondary radar stations.

Sân bay Long Thành trước

Long Thanh Airport weather radar station

In the central area, the Long Thanh Air Traffic Control Tower – an architectural highlight with its lotus-bud design and 123m-high control tower – has been completed along with supporting facilities on a total area of ​​24,000 m2. In addition, the airport's "eyes" including primary and secondary radar stations, radio broadcasting systems, and multi-directional navigation stations have also been fully installed on an area of ​​approximately 70,000 m2.

A representative from VATM affirmed that the unit is ready to take control of the airspace at this new mega-airport with a complete technical system and internationally qualified personnel. A special feature of this deployment is the application of a "multi-layered, multi-tiered" safety standard. Essential systems such as communication, navigation, and surveillance are not only undergoing stable trial operation but also have multi-layered backup mechanisms, ensuring continuous 24/7 operation and minimizing the risk of disruption even in bad weather or complex technical incidents.

The runway is lit up, awaiting the arrival of the "iron bird".

Sân bay Long Thành trước

Runway 1 at Long Thanh Airport is illuminated. Photo: ACV

Sân bay Long Thành trước

A panoramic view of runway 1 and the passenger terminal at Long Thanh Airport. Photo: ACV

Parallel to the progress of the air traffic control tower, the Vietnam Airports Corporation (ACV) is also urgently completing the items at the airfield. On the evening of December 11th, runway 1 (23L/05R) of Long Thanh airport officially lit up, marking its readiness for a test flight.

The navigation lights here utilize 100% imported LED technology from Europe, combined with a precision landing guidance system (ILS/DME). This combination is considered an advanced technological solution, helping to guide aircraft to approach and land with absolute precision even in conditions of limited visibility. In fact, this navigation light system was successfully tested on the evening of April 26, 2025, for prior calibration flights.

Currently, cleaning of the runway, taxiway B, and connecting taxiways has been completed, ensuring that all conditions are met to receive aircraft according to the actual operating scenario.

Flight test scenarios and airspace challenges

Sân bay Long Thành trước

The Long Thanh airport terminal is now taking shape.

According to the plan, the historic technical flights will utilize modern large aircraft such as the Boeing 787 and A350. Specifically, on December 15th, a flight will depart from Tan Son Nhat Airport to Long Thanh and return, with a flight time of approximately 40 minutes. Following that, on December 19th, another flight is scheduled to depart from Noi Bai Airport and land in Long Thanh.

To achieve this, one of the biggest challenges the engineering team has overcome is optimizing airspace. Due to Long Thanh's geographical location being very close to Tan Son Nhat International Airport and Bien Hoa military airport, air traffic control is extremely complex. After years of collaboration with Boeing Corporation, VATM has developed an optimized flight procedure that meets the requirements for simultaneous operation of both major airports in the Southeast region. This procedure has been approved by the Civil Aviation Authority and will officially be implemented from December 19, 2025.

Human factors and emergency scenarios

Besides preparing the equipment, the human factor is also given top priority. On December 10th, the Civil Aviation Authority conducted training on a simulator (SIM) for air traffic controllers at Long Thanh, with exercises focusing on handling challenging situations such as bad weather or equipment malfunctions.

Sân bay Long Thành trước

Long Thanh Air Traffic Control Tower

Sân bay Long Thành trước

VATM is devoting all its resources to installing equipment systems at the Long Thanh Air Traffic Control Tower.

The operational forces at Long Thanh Air Traffic Control Tower, Tan Son Nhat Approach Center, and Ho Chi Minh City Long-Distance Control Center have been trained to coordinate closely. Detailed scenarios for handling anomalies, from loss of communication and aircraft technical malfunctions to security situations such as illegal interference by unmanned aerial vehicles (UAVs), have been developed. Even a plan for diverting to Tan Son Nhat has been carefully considered to ensure readiness for any situation.

Sân bay Long Thành trước
Sân bay Long Thành trước
Sân bay Long Thành trước

Component three of the Long Thanh airport project includes essential facilities such as the terminal and runway.

Meanwhile, at component project 3, contractors are also racing against time to construct the passenger terminal. The main structural elements have been largely completed, making way for the installation of specialized equipment such as baggage conveyors, security screening systems, and interior finishing, to ensure consistency between engineering and architecture when the airport officially opens.

The upcoming first technical flight is not only a test of the investor's and air traffic control's capabilities but also a milestone affirming Vietnam's aviation position in mastering technology at this key national project.

Source: https://vtv.vn/san-bay-long-thanh-truoc-gio-g-hoan-tat-kich-ban-don-sieu-may-bay-boeing-787-100251212135030171.htm


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product