Vietnam.vn - Nền tảng quảng bá Việt Nam

Ho Chi Minh City requires completion of payment and handover of land for the Ho Chi Minh City - Moc Bai expressway project in 2025

Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc requested localities to complete compensation, support, and resettlement payments for people affected by the Ho Chi Minh City - Moc Bai Expressway project in 2025 and speed up construction progress.

Báo Tuổi TrẻBáo Tuổi Trẻ23/10/2025

TP.HCM yêu cầu hoàn tất chi trả, giao mặt bằng dự án cao tốc TP.HCM - Mộc Bài trong năm 2025 - Ảnh 1.

Chairman of Ho Chi Minh City People's Committee Nguyen Van Duoc inspected the Ring Road 3 project, Ho Chi Minh City - Moc Bai Expressway on October 1 - Photo: CHAU TUAN

The above important contents are part of the conclusion of Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc and the working delegation on the field trip to the Ho Chi Minh City - Moc Bai Expressway and Ring Road 3 project on October 1. The delegation also included Vice Chairman of the City People's Committee Bui Xuan Cuong, Vice Chairman of the City People's Committee Bui Minh Thanh and representatives of departments, branches and localities.

After the meeting, Chairman Nguyen Van Duoc acknowledged the efforts of the units in implementing the project, and emphasized that these are two vital traffic axes that are important in expanding the development space for Ho Chi Minh City and neighboring areas. However, the progress is still slow, the disbursement rate is low compared to the plan.

The main reason is that some localities and units still lack determination, initiative and flexibility in handling work.

Besides, coordination is not yet synchronized, there are still problems with compensation, resettlement and prolonged administrative procedures.

"Units need to focus, mobilize all resources, and proactively carry out assigned tasks to make up for slow progress" - Mr. Duoc's conclusion.

For the Ho Chi Minh City - Moc Bai expressway project, the Chairman of the Ho Chi Minh City People's Committee assigned localities to promptly establish and perfect the commune-level Steering Committee, regularly review the progress of compensation, support, resettlement, and remove difficulties and obstacles.

The commune-level steering committee will have an additional mobilization and propaganda team consisting of local people, people who are knowledgeable about the area, have experience in compensation, persuade people to agree with the policy and promptly hand over the site to the investor. The deadline for completing mobilization and handing over the site is set before October 22, 2025.

Localities need to be proactive and flexible in compensation payments, ensuring compliance with regulations, and absolutely not allowing loss or negativity to occur.

Communes must complete the appraisal and approval of compensation, support and resettlement plans no later than October 2025, and make payments to all affected households by December 2025.

The Ho Chi Minh City Department of Transport is assigned to preside over and work with relevant departments and branches to complete procedures, design construction, select investors and contractors according to regulations, and ensure the construction progress is on schedule.

Specifically, component project 1 will start construction in the first quarter of 2026, component project 2 will start construction of Provincial Road 8 overpass in November 2025 and the remaining items before December 19, 2025.

The Department of Finance was assigned to preside over and coordinate with the City People's Committee's advisory agencies to report to the City Party Committee Standing Committee on supporting compensation and resettlement capital for Tay Ninh province (where the expressway passes through).

At the same time, localities must strengthen management and prevent "land brokers", "compensation brokers", and "document brokers" from taking advantage of project implementation to profit and cause disorder.

cao tốc TP.HCM - mộc bài - Ảnh 3.

The construction site of the Ring Road 3 project through the old Cu Chi district (HCMC), which is also the first section of the HCMC - Moc Bai expressway - Photo: CHAU TUAN

Regarding the Ho Chi Minh City Ring Road 3 project, the Chairman of the Ho Chi Minh City People's Committee requested the Department of Construction to coordinate with relevant units to urgently remove obstacles and ensure the traffic opening progress as committed.

For the Beltway 4 project through Ho Chi Minh City, the Department of Construction was assigned to review material sources and calculate appropriate construction structures to ensure supply.

Director of the Department of Construction Tran Quang Lam directly directs and supervises the progress of traffic infrastructure projects, promptly reports to city leaders to handle problems.

Vice Chairman of the City People's Committee Bui Xuan Cuong will be responsible for directing the construction progress of the projects, while Vice Chairman Bui Minh Thanh will be in charge of the site clearance progress.

Back to topic
CHAU TUAN

Source: https://tuoitre.vn/tp-hcm-yeu-cau-hoan-tat-chi-tra-giao-mat-bang-du-an-cao-toc-tp-hcm-moc-bai-trong-nam-2025-20251023105744241.htm


Comment (0)

No data
No data

Same tag

Same category

Stunningly beautiful terraced fields in Luc Hon valley
'Rich' flowers costing 1 million VND each are still popular on October 20th
Vietnamese Films and the Journey to the Oscars
Young people go to the Northwest to check in during the most beautiful rice season of the year

Same author

Heritage

Figure

Enterprise

Young people go to the Northwest to check in during the most beautiful rice season of the year

News

Political System

Destination

Product