Vietnam.vn - Nền tảng quảng bá Việt Nam

Ho Chi Minh City requires completion of payment and handover of land for the Ho Chi Minh City - Moc Bai expressway project in 2025

Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc requested localities to complete compensation, support, and resettlement payments for people affected by the Ho Chi Minh City - Moc Bai Expressway project in 2025 and speed up construction progress.

Báo Tuổi TrẻBáo Tuổi Trẻ23/10/2025

TP.HCM yêu cầu hoàn tất chi trả, giao mặt bằng dự án cao tốc TP.HCM - Mộc Bài trong năm 2025 - Ảnh 1.

Chairman of the Ho Chi Minh City People's Committee Nguyen Van Duoc inspects the Ring Road 3 project and the Ho Chi Minh City - Moc Bai expressway on October 1st - Photo: CHAU TUAN

The above important points are included in the conclusions of the Ho Chi Minh City People's Committee Chairman Nguyen Van Duoc and the working group's field visit to the Ho Chi Minh City - Moc Bai expressway and Ring Road 3 project on October 1st. The delegation also included Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong, Vice Chairman of the Ho Chi Minh City People's Committee Bui Minh Thanh, and representatives from various departments, agencies, and localities.

Following the meeting, Chairman Nguyen Van Duoc acknowledged the efforts of the units in implementing the project, while emphasizing that these two vital transportation arteries are crucial for expanding the development space of Ho Chi Minh City and the surrounding areas. However, progress remains slow, and the disbursement rate is lower than planned.

The main reason is that some localities and units still lack decisiveness, proactiveness, and flexibility in handling work.

In addition, coordination is not synchronized, and there are still obstacles regarding compensation, resettlement, and lengthy administrative procedures.

"The units need to focus, mobilize all resources, and proactively carry out their assigned tasks to compensate for the delays," concluded Mr. Duoc.

Regarding the Ho Chi Minh City - Moc Bai expressway project, the Chairman of the Ho Chi Minh City People's Committee instructed local authorities to urgently establish and strengthen the commune-level steering committees, regularly review the progress of compensation, support, and resettlement, and resolve difficulties and obstacles.

The commune-level steering committee will have an additional mobilization and propaganda team consisting of local people who are familiar with the area and have experience in compensation and persuading people to agree with the policy and hand over the land to the investor as soon as possible. The deadline for completing the mobilization and land handover is set before October 22, 2025.

Local authorities need to be proactive and flexible in paying compensation, ensuring compliance with regulations and absolutely preventing any losses or corruption.

Communes must complete the assessment and approval of compensation, support, and resettlement plans no later than October 2025, and disburse payments to all affected households by December 2025.

The Ho Chi Minh City Department of Transport is tasked with coordinating with relevant departments and agencies to complete procedures, design construction, select investors and contractors in accordance with regulations, and ensure the project commences on schedule.

Specifically, component project 1 will commence in Q1 2026, component project 2 will begin construction of the Provincial Road 8 overpass in November 2025, and the remaining items will be completed before December 19, 2025.

The Department of Finance is tasked with leading and coordinating with the agencies advising the People's Committee of Ho Chi Minh City to report to the Standing Committee of the City Party Committee on providing capital support for compensation and resettlement in Tay Ninh province (where the expressway passes through).

At the same time, localities must strengthen management and prevent the exploitation of land brokers, compensation brokers, and document brokers who take advantage of project implementation for personal gain, causing disorder.

cao tốc TP.HCM - mộc bài - Ảnh 3.

The construction site of the Ring Road 3 project through the former Cu Chi district (Ho Chi Minh City), which is also the starting point of the Ho Chi Minh City - Moc Bai expressway - Photo: CHAU TUAN

Regarding the Ho Chi Minh City Ring Road 3 project, the Chairman of the People's Committee of Ho Chi Minh City requested the Department of Construction to coordinate with relevant units to urgently resolve obstacles and ensure the project opens to traffic as committed.

For the Ring Road 4 project section passing through Ho Chi Minh City, the Department of Construction has been tasked with reviewing material sources and calculating appropriate construction structures to ensure supply.

Director of the Department of Construction Tran Quang Lam directly supervises and monitors the progress of transportation infrastructure projects, promptly reporting any obstacles to the city leadership for resolution.

Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong will be responsible for directing the construction progress of the projects, while Vice Chairman Bui Minh Thanh will be in charge of the land clearance progress.

Back to the topic
CHAU TUAN

Source: https://tuoitre.vn/tp-hcm-yeu-cau-hoan-tat-chi-tra-giao-mat-bang-du-an-cao-toc-tp-hcm-moc-bai-trong-nam-2025-20251023105744241.htm


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Don Den – Thai Nguyen's new 'sky balcony' attracts young cloud hunters

News

Political System

Destination

Product