Vietnam.vn - Nền tảng quảng bá Việt Nam

Huong Son Hydropower Plant to be operational in Q4/2024

Việt NamViệt Nam06/09/2024


The Huong Son Hydropower Plant investment project has a total installed capacity of 39.4 MW, connected to the national power grid at the 2x25MVA-110/35/22KV Linh Cam – Ha Tinh substation.

The Management Board of Ha Tinh Economic Zone issued Decision No. 186/QD-KKT approving the adjustment of the investment policy for the Huong Son Hydropower Plant project.

Previously, the Project had been approved for adjustment by this Board in Decision No. 01/QD-KKT dated January 2, 2024.

Nhà máy thuỷ điện Hương Sơn
Huong Son Hydroelectric Power Plant.

Accordingly, the implementation schedule has been adjusted as follows: "Implementation schedule – Phase 2 – Huong Son 2 Hydropower Plant will commence in Q1/2021 and be completed and put into operation in Q4/2024".

The Management Board of Ha Tinh Economic Zone has assigned Huong Son Hydropower Joint Stock Company the responsibility to focus all resources on construction and completion, bringing the project into operation according to the approved schedule and objectives.

The land area to be used is 189,107 hectares. The project implementation period is 50 years from August 25, 2008 (the date of initial issuance of the investment certificate).

The Huong Son Hydropower Plant investment project has a total installed capacity of 39.4 MW, connected to the national power grid at the 2x25MVA-110/35/22KV Linh Cam – Ha Tinh substation, divided into 2 phases.

Phase 1 of the project has a capacity of 33 MW (Huong Son 1 Hydropower Plant), consisting of two scoop turbine units, each with a capacity of 16.5 MW. Phase 2 has a capacity of 6.4 MW (Huong Son 2 Hydropower Plant), consisting of two units, each with a capacity of 3.2 MW. The project's objective is to invest in, construct, manage, and operate the hydropower plant and produce and sell electricity.

The total investment capital for the project is over VND 1,103.766 billion, of which phase 1 has a total capital of over VND 812.444 billion (equity capital of over VND 231.539 billion and borrowed capital of over VND 580.904 billion); phase 2 has a total investment capital of over VND 291.322 billion (equity capital of VND 91.322 billion and borrowed capital of VND 200 billion).

Regarding the implementation schedule, Phase 1 commenced in 2005 and was completed and put into operation in 2012; Phase 2 commenced in the first quarter of 2021 and was completed and put into operation in the fourth quarter of 2024. The project is located in Son Kim 1 commune, Huong Son district, Ha Tinh province (within the Cau Treo International Border Gate Economic Zone).

Source: https://baodautu.vn/ha-tinh-nha-may-thuy-dien-huong-son-van-hanh-trong-quy-iv2024-d224021.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product