Accordingly, immediately after receiving the dossier of site clearance markers for Component Project 1: Infrastructure investment connecting stations on the route and station square, the Lao Cai - Coc San Regional Project Management Board organized a census and counting of households in the affected area.

ground
Mr. Pham Anh Hung - Deputy Director of the Lao Cai - Coc San Regional Construction Project Management Board said: To ensure that the statistics and counting work is carried out publicly, transparently, and to the right subjects, the staff of the Project Management Board and representatives of households have reviewed and declared each item in detail according to current regulations of the law.
Previously, the Lao Cai - Coc San Regional Construction Investment Project Management Board held a meeting to publicize project information, compensation and site clearance policies, and resettlement locations; and directly answered people's questions related to compensation and site clearance support policies.

Households in the affected area all agree with the State's policy and hope that relevant agencies will speed up the progress of resettlement areas so that people can soon stabilize their lives.
Mr. Dang Quang De, Son Man 2 village, Lao Cai ward said: My family moved here to live for nearly ten years, now we have to move to a new place to start a new life from scratch, which is a bit worrying, but we also determined that this is a key project of the State, so complying so that the project can be implemented soon is the responsibility of each person.

Mr. Nguyen Van Nhat - Chairman of Lao Cai Ward People's Committee said: Currently, all works are being carried out in parallel, including statistics, counting, determining resettlement locations, approving payment of funds to people and organizations. Through understanding public opinion, people and organizations all agree with the State's policies and support mechanisms and policies for compensation and site clearance.
Mr. Nguyen Van Nhat added: Currently, there is only one problem related to the unit price of assets and structures of units in Dong Pho Moi Industrial Park. With this content, the Ward People's Committee has hired a consulting unit to carry out the steps of counting and valuation, then carry out the next steps to pay.

The location where the groundbreaking ceremony will be held is on a 6.8-hectare plot of land, planned for the new Lao Cai station. This plot of land is located in the Dong Pho Moi Industrial Park, has been leveled, and has a convenient traffic system. On the morning of March 12, a unit under the Provincial Economic Zone Management Board with headquarters in this area is clearing facilities and trees to hand over the site.
During a recent trip to inspect the project's progress and work with Lao Cai province leaders, Deputy Minister of Construction Nguyen Danh Huy noted that preparations for the groundbreaking ceremony need to be carefully prepared for all items, because Lao Cai is the main bridge point.

At the recent meeting to evaluate the progress and agree on the plan for implementing the site clearance work, comrade Trinh Viet Hung - Alternate member of the Party Central Committee, Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council, Head of the Steering Committee for Site Clearance of the Lao Cai - Hanoi - Hai Phong Railway Construction Investment Project, the section passing through Lao Cai province requested the Steering Committee, the Steering Committee's Support Team, relevant departments, branches and localities to focus on ensuring the conditions for the project groundbreaking ceremony on December 19 to take place safely, in accordance with the requirements set by the Central Government and the province.

Along with the preparation work for the project's groundbreaking, these days, construction units are taking advantage of favorable weather to dig and fill soil and rock, level the resettlement projects to serve the site clearance for the Lao Cai - Hanoi - Hai Phong high-speed railway project, contributing to ensuring the project's progress as required by the Government.
Source: https://baolaocai.vn/san-sang-mat-bang-chuan-bi-cho-le-khoi-cong-du-an-duong-sat-lao-cai-ha-noi-hai-phong-post888088.html