On July 18, the Lam Dong Provincial People's Committee delegation surveyed the starting point of the expressway and the locations of resettlement area construction projects in Ward 1, Bao Loc, Bao Lam 2 Commune, Di Linh Commune, Hoa Ninh Commune and Duc Trong Commune, Lam Dong Province.

According to the Lam Dong Province Construction Investment Project Management Board, resettlement areas are currently in the investment preparation stage and have not yet begun construction. build
In addition, there are signs of tree planting and construction expansion while the project is carrying out land acquisition procedures.

At the meeting, localities where the project passes through also raised outstanding issues focusing on compensation for site clearance, inventory of architectural objects and crops; and difficulties in assessing compensation prices.
Faced with these difficulties, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai directed relevant departments to guide commune-level authorities on detailed procedures for implementing unit prices and land valuation in site clearance. In addition, for material mines, Mr. Nguyen Hong Hai also assigned units to carefully prepare for mining licenses, ensuring stability during the construction process...
The Bao Loc - Lien Khuong Expressway project was started by the Lam Dong Provincial People's Committee on June 29, 2025. However, up to now, the implementation of the tasks of compensation, support, resettlement; establishment, appraisal and approval of land prices; surveying and mapping of land acquisition... has not been completed and is behind schedule due to changes in administrative boundaries and the absence of district-level authorities.
Source: https://www.sggp.org.vn/sau-khoi-cong-du-an-cao-toc-bao-loc-lien-khuong-van-ngon-ngang-thu-tuc-post804386.html