After groundbreaking, Bao Loc - Lien Khuong expressway project is still facing a lot of paperwork

After inspecting the construction progress of the Bao Loc - Lien Khuong expressway project, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai directed departments and branches to urgently coordinate and remove obstacles related to this project.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng18/07/2025

On July 18, the Lam Dong Provincial People's Committee delegation surveyed the starting point of the expressway and the locations of resettlement area construction projects in Ward 1, Bao Loc, Bao Lam 2 Commune, Di Linh Commune, Hoa Ninh Commune and Duc Trong Commune, Lam Dong Province.

IMG_3954.jpeg
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai (left cover) surveys and directs problems related to the Bao Loc - Lien Khuong expressway project.

According to the Lam Dong Province Construction Investment Project Management Board, resettlement areas are currently in the investment preparation stage and have not yet begun construction. build

In addition, there are signs of tree planting and construction expansion while the project is carrying out land acquisition procedures.

IMG_3955.jpeg
Route map of Bao Loc - Lien Khuong expressway in the expressway system connecting Ho Chi Minh City to Da Lat

At the meeting, localities where the project passes through also raised outstanding issues focusing on compensation for site clearance, inventory of architectural objects and crops; and difficulties in assessing compensation prices.

Faced with these difficulties, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai directed relevant departments to guide commune-level authorities on detailed procedures for implementing unit prices and land valuation in site clearance. In addition, for material mines, Mr. Nguyen Hong Hai also assigned units to carefully prepare for mining licenses, ensuring stability during the construction process...

The Bao Loc - Lien Khuong Expressway project was started by the Lam Dong Provincial People's Committee on June 29, 2025. However, up to now, the implementation of the tasks of compensation, support, resettlement; establishment, appraisal and approval of land prices; surveying and mapping of land acquisition... has not been completed and is behind schedule due to changes in administrative boundaries and the absence of district-level authorities.

Source: https://www.sggp.org.vn/sau-khoi-cong-du-an-cao-toc-bao-loc-lien-khuong-van-ngon-ngang-thu-tuc-post804386.html


Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product