The Ring Road 4 Elevated Expressway - Capital Region has a construction period of 2 years.

The Hanoi Traffic Construction Investment Project Management Board said it is completing the final investment preparation procedures to serve the groundbreaking ceremony of Component Project 3 - the expressway under the Ring Road 4 project - Capital Region on August 19.

Báo Công an Nhân dânBáo Công an Nhân dân01/08/2025

According to the approval decision, the elevated highway of the Ring Road 4 project - Capital Region has the starting point at Km 3+695 on Noi Bai - Lao Cai highway ( Hanoi city area); the end point at Km 40+500 on Noi Bai - Ha Long highway (Bac Ninh province area).

The total length of the route is about 113.5km, of which: The main route is about 103.8km long, running through Hanoi city (57.52km), Hung Yen province (about 19.3km), Bac Ninh province (about 27km) and the 9.7km section connecting Ring Road 4 with Noi Bai - Ha Long highway.

August 19: Hanoi plans to start construction of the Ring Road 4 elevated highway - Capital Region -0

The route is designed according to expressway standards, speed 100km/h; phase 1 invested in 4 lanes (phase 2 completed with 6 lanes and emergency lanes on each side). In the first investment phase, the Ring Road 4 elevated expressway has a road surface width of 17.0m; bridge width of 17.5m. Particularly, the bridges over the Red River and Duong River were completed for both phases, so the bridge surface has a width of 24.5m and is arranged with 2 more lanes for motorbikes and rudimentary vehicles to pass through the bridge.

The project will invest in the construction of 8 complete interchanges. Of which 5 are in Hanoi; 2 are in Hung Yen province; 1 is in Bac Ninh province. At the same time, the project will invest in the construction of 7 branches connecting to the parallel roads on both sides. The total investment of the project is 56,500 billion VND, mobilized in the form of public-private partnership (PPP) investment, BOT contract - accounting for 65% of the total investment of the Ring Road 4 - Capital Region project.

Once started, the elevated highway project will take 2 years to construct and be completed in 2027.

Source: https://cand.com.vn/Giao-thong/duong-cao-toc-tren-cao-vanh-dai-4-vung-thu-do-co-thoi-gian-thi-cong-2-nam-i776780/


Comment (0)

Please leave a comment to share your feelings!

Same category

Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy
Bui Cong Nam and Lam Bao Ngoc compete in high-pitched voices
Vietnam is the world's leading Heritage Destination in 2025

Same author

Heritage

Figure

Enterprise

Knock on the door of the fairyland of Thai Nguyen

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC