The Hanoi People's Committee has just submitted a document to the Hanoi People's Council requesting approval of the adjustment of the investment policy for the Tran Hung Dao Bridge Construction Investment Project. It is expected that the document will be considered and approved by the Hanoi People's Council at the thematic meeting held on September 23.
In Resolution No. 10/NQ-HDND dated February 25 of the Hanoi People's Council, the Tran Hung Dao Bridge Construction Investment Project has a total length of about 5.6km. The starting point is Tran Hung Dao - Tran Thanh Tong Intersection (Hoan Kiem District); the end point connects with Vu Duc Than Street (Long Bien District). The project has a total investment of about 15,967 billion VND.
Now, the Hanoi People's Committee has proposed to adjust the Tran Hung Dao Bridge Construction Investment Project with a total route length of about 4.18km. Adjust the project implementation location. The starting point of the route is the intersection of Tran Hung Dao - Tran Thanh Tong - Le Thanh Tong (Cua Nam ward, Hai Ba Trung); the end point connects with Nguyen Son street (belonging to Long Bien and Bo De wards). The preliminary adjustment of the total investment is about 16,226 billion VND.

Perspective of Tran Hung Dao Bridge over the Red River (Hanoi). Photo: Design unit
The Hanoi People's Committee also proposed to adjust the project division plan. Specifically, the GPMB project group includes 3 projects. Of which, project TP 1.1 and 1.2 is invested by Hong Ha Ward People's Committee; project TP 1.3 is invested by Long Bien Ward People's Committee.
For the Construction Investment Project group, including City Project 2.1: Investment in construction and renovation of Co Linh - Hong Tien road at the intersection of Co Linh road and Tran Hung Dao bridge, with the Traffic Construction Investment Project Management Board as the investor.
Investment scope: Renovating Co Linh - Hong Tien road at Co Linh intersection with Tran Hung Dao bridge with a length of 694.84m and technical infrastructure system on the road. The length of the branch connecting Lam Du - Hong Tien is about 147.46m. The length of the branch connecting Co Linh - Bat Khoi is about 94.33m.
Investment scale: Co Linh - Hong Tien road within the renovated intersection is moved towards the airport about 9.5m to arrange branch intersections connecting Tran Hung Dao bridge with Co Linh road.
The road cross-section ensures 6 lanes with a median of 0.5m; the sidewalks on both sides are 5m. After leaving the intersection, the existing road cross-section has a cross-section of 40m and a length of about 694.84m.
Project TP 2.2: Investment in construction of Tran Hung Dao bridge, implemented under the public-private partnership (PPP) method, Build-Transfer (BT) contract, payment by land fund. The approach roads at both ends of the bridge are invested with a cross-section of 25.5m - 30m with a total length of about 1.42km.
The main bridge over the Red River is built permanently according to current bridge design standards; the main bridge structure is steel arch, arch shape; the main bridge length is 870m, cross-section scale is about 43m, ensuring 6 lanes for motor vehicles, 2 lanes for bicycles, 2 lanes for pedestrians.
Approach bridge: Hoan Kiem district side (now Hoan Kiem, Hong Ha, Hai Ba Trung wards) has a cross-section scale varying from 26m to 41.5m ensuring 6 lanes of motor vehicles. The total length of the approach bridge is about 1,213m.
Complete construction investment at 3 intersections including: Different-level intersection with Tran Khanh Du - Nguyen Khoi street; intersection with Ta Hong dike road and Co Linh street; level intersection with Nguyen Son street.
The preliminary payment method is 4 land plots with a total area of 635.45 hectares. The location, area, planning information, expected value of the land fund for payment, and payment method will be officially determined when the project is submitted for appraisal and approval according to regulations, specifically: Land plot in Phu Dong commune (formerly Yen Thuong commune, Gia Lam district), about 25.45 hectares.
Land plot in Dong Anh commune (formerly Mai Lam commune and Dong Hoi commune, Dong Anh district), research area scale of about 56 hectares; land plot in Dong Anh commune (formerly Dong Hoi commune, Dong Anh district), research area scale of about 49 hectares; part of land plot in Phu Dong commune, Dong Anh commune (Gia Lam district, old Dong Anh district), proposed research area scale of about 505 hectares.
Source: https://cand.com.vn/Giao-thong/ha-noi-de-xuat-doi-635-ha-dat-de-xay-cau-tran-hung-dao-i781960/