More than 70% of the construction volume of dike repair projects has been completed.

The 2025 dike maintenance project in the eastern area of ​​Hai Phong has completed an average of more than 70% of the volume of construction items.

Báo Hải PhòngBáo Hải Phòng08/12/2025

construction 1
Construction of reinforcement and repair of the right dike of the New River.

According to the Department of Agriculture and Environment, by December 7, the 2025 dike maintenance project in the eastern area of ​​Hai Phong had completed an average of more than 70% of the construction volume of project items.

In which, package No. 6 is grouting to reinforce the dike body at K33+000 - K36+000 of Hoa left dike, K10+000 - K12+800 of Thai Binh left dike and package No. 5 is repairing the dike toe and slope; adjusting and clearing the slope, repairing the embankment, filling potholes and erosion grooves on the dike surface, basically completed.

Currently, the investor is focusing on urging construction units to speed up the progress of package 4 to reinforce and repair the dike surface on the right side of Thai Binh, right side of Cam, left side of Cam, right side of Moi, left side of Thai Binh, left side of Van Uc and package 7 to build 4 warehouses for flood and storm prevention materials combined with dike watchtowers.

construction 2
Construction packages for embankment reinforcement and repair in the city are being accelerated.

The 2025 dike maintenance project was approved by the Department of Dike Management and Natural Disaster Prevention and Control in Decision No. 504/QD-DD-QLDD dated October 2, 2025 with a total investment of 40 billion VND from the 2025 irrigation, dike, and natural disaster prevention economic career fund managed by the Ministry of Agriculture and Environment ; construction will be implemented in the old Hai Phong city.

The project consists of 4 packages 4, 5, 6 and 7. There are currently 2 packages 4 and 7 remaining, the construction units are striving to complete the entire project and put it into operation by December 30, 2025.

The dike restoration projects, once completed, will contribute to overcoming the degradation and damage of the dike system in the city, improving disaster prevention capacity.

PROGRESS

Source: https://baohaiphong.vn/hoan-thanh-hon-70-khoi-luong-thi-cong-cac-cong-trinh-tu-bo-de-dieu-528977.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy
Bui Cong Nam and Lam Bao Ngoc compete in high-pitched voices
Vietnam is the world's leading Heritage Destination in 2025

Same author

Heritage

Figure

Enterprise

Knock on the door of the fairyland of Thai Nguyen

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC