The projects inspected this time include: the Bà Tá - Trà Tân road upgrade and expansion project; the road project from Tân Minh commune to Sơn Mỹ commune; the DT.719 bypass road and bridge over the Dinh River in La Gi ward; the DT.719B coastal road project from Hòn Lan to Tân Hải; the new DT.719B coastal road project from Phan Thiết to Kê Gà; and the Văn Thánh bridge project located on the Cà Ty River in Tiến Thành and Bình Thuận wards.

Specifically, the Bà Tá - Trà Tân road upgrade and expansion project has a length of 15.1km, a roadbed width of 7.5m, and a road surface width of 6.5m. The road surface is asphalt concrete, with earthen shoulders, a drainage system, and ensures traffic safety.
The total investment for the project is VND 102.165 billion from the provincial budget. The implementation period is until the end of 2025. The project has currently reached 98% of the contract volume. To date, VND 22.286 billion has been disbursed, reaching a rate of 69.43%.

The road project from Tan Minh commune to Son My commune has a total length of 23.71 km. The road surface is asphalt concrete. The project includes the construction of three new reinforced concrete bridges: Song Dinh Bridge (82.2m long), Song Gieng Bridge (82.1m long), and Tan Duc Bridge (107.5m long). Simultaneously, investment will be made in lighting, water supply and drainage systems, traffic safety, and other supporting facilities.
The total investment for the project is VND 682.26 billion; of which, the central government budget is VND 348 billion, and the provincial budget for the period 2026-2030 is VND 334.26 billion. The project implementation period is 4 years. The project is expected to be completed in September 2027.
The DT.719 bypass road and bridge over the Dinh River in La Gi ward has a length of 6,820.4m. The project has a total investment of 212.9 billion VND. The project implementation period is 4 years, expected to be completed in 2028. To date, the project has disbursed 15.178 billion VND, reaching 30.25%.

The DT.719B coastal road project, specifically the Hon Lan - Tan Hai section, has a total length of approximately 10.4 km. The total investment for the project is VND 663.883 billion. Currently, about 94% of the project's land has been handed over, meeting the construction schedule.

The project to upgrade the DT.719B coastal arterial road section from Phan Thiet to Ke Ga has a length of 25.61km, a roadbed width of 28m, a road surface width of 16m, a central median of 11m, and reinforced shoulders of 0.5m on each side. The total investment for the project is VND 1,274.317 billion.
The Van Thanh Bridge project is located on the Ca Ty River in Tien Thanh and Binh Thuan wards. The total investment for the project is 225.2 billion VND from central government funds, with a construction period of 4 years. To date, the project has achieved approximately 55% of the contract volume.

Inspections have revealed that most projects are facing obstacles related to land acquisition, lack of land prices, and failure to locate landowners. Currently, only La Gi and Phuoc Hoi wards have achieved their compensation and land clearance targets and have implemented land price determinations.
Speaking at the meeting, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai directed that Suoi Kiet commune must accelerate the progress and complete the compensation work for the upgrading and expansion project of Ba Ta - Tra Tan road before December 31, 2025. For Ham Tan, Son My, and Tan Minh communes, they need to immediately coordinate with the Lam Dong Provincial Land Development Center Branch 1 to focus on land valuation so that compensation prices can be applied to households as soon as possible.
Specifically, for the DT.719B coastal road project, the Hon Lan - Tan Hai section already has available land, so manpower and machinery must be increased to ensure construction proceeds on schedule. The Department of Agriculture and Environment will assist in completing the procedures for changing the land use purpose of the forest land within the project area.
Regarding the Van Thanh Bridge Project, delays have occurred due to issues with alluvial land and disagreements among residents regarding the difference in land prices. The Vice Chairman of the Provincial People's Committee has instructed Tien Thanh ward and relevant units to promptly review and apply compensation rates for the remaining 8 households according to regulations, in order to ensure the construction progress and disbursement of funds.
Source: https://baolamdong.vn/lam-dong-doc-thuc-tien-do-6-du-an-giao-thong-phia-dong-nam-tinh-396101.html