Dredging of many shipping routes is about to be completed.

Báo Xây dựngBáo Xây dựng29/12/2024

Besides the dredged shipping routes that have been completed as planned, there are still routes that have to adjust the implementation time due to environmental procedure problems.


According to the Vietnam Maritime Administration, dredging and maintenance projects to be carried out in 2023-2024 on 11 basic waterways have been basically completed.

In particular, some maritime routes have completed dredging and been accepted for operation, including Hai Thinh channel, a channel for large tonnage ships entering the Hau River, Hon La maritime route, Thuan An maritime route, and Sa Ky maritime route. The projects are currently in the process of finalizing the project.

Sắp hoàn tất nạo vét nhiều tuyến luồng hàng hải- Ảnh 1.

Many dredging projects are under construction and will be completed in 2024 (Illustration photo).

In addition, many projects have completed bidding procedures to select contractors and are under construction, and will be completed in December, such as the dredging and maintenance project of Hai Phong maritime channel (Lach Huyen section), Cua Lo maritime channel, Saigon - Vung Tau maritime channel and Diem Dien maritime channel.

Regarding the Da Nang waterway dredging maintenance project, the Vietnam Maritime Administration said the project's completion date has been adjusted to 2025 due to problems with environmental procedures.

The Soai Rap waterway has been stopped due to the inability to arrange a location to dump dredged material.

In 2024, there will be 2 channels that will be dredged and maintained, including the channel Hai Phong maritime 2022-2025 (Ha Nam and Bach Dang canal sections) and Rach Gia channel.

Of which, the Hai Phong channel project has completed dredging and is completing procedures to organize acceptance and put into operation. The Rach Gia channel is also under construction, expected to be completed in December 2024.

In the period of 2024-2025, 12 waterways will be dredged and maintained. The Vietnam Maritime Administration is selecting a project management unit and implementing environmental procedures according to the provisions of Decree No. 57/2024 of the Government regulating the management of dredging activities in seaport waters and inland waterway waters.



Source: https://www.baogiaothong.vn/sap-hoan-tat-nao-vet-nhieu-tuyen-luong-hang-hai-192241229154442145.htm

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Notre Dame Cathedral in Ho Chi Minh City is brightly lit to welcome Christmas 2025
Hanoi girls "dress up" beautifully for Christmas season
Brightened after the storm and flood, the Tet chrysanthemum village in Gia Lai hopes there will be no power outages to save the plants.
The capital of yellow apricot in the Central region suffered heavy losses after double natural disasters

Same author

Heritage

Figure

Enterprise

Dalat coffee shop sees 300% increase in customers because owner plays 'martial arts movie' role

News

Political System

Destination

Product