
At the meeting, representatives from the regional investment and construction project management boards presented a summary of the progress of public investment projects in their respective areas over the past period. They also outlined tasks for implementation in the remaining months of 2025.

According to the report, the Tuy Phong Area Investment and Construction Project Management Board has disbursed over 112/212.4 billion VND, reaching nearly 53% of the 2025 capital plan. In the coming period, the Board will urge construction units to focus manpower, machinery and equipment to accelerate progress and organize project acceptance when work is completed.
It is expected that by the end of the year, the Regional Investment and Construction Project Management Board will have disbursed over 95% of the planned capital and will continue to strive for even better results by January 31, 2026.
For the North Binh Area Investment and Construction Project Management Board, the planned capital for 2025 is over 181.3 billion VND, and as of the reporting date, approximately 56% has been disbursed. In the remaining months, the unit will continue to coordinate with relevant parties to resolve difficulties and obstacles in some projects to accelerate implementation progress. It is expected that by the end of the year, over 95% of the allocated capital will be disbursed.

As of October 20, 2025, the Ham Thuan Bac Area Investment and Construction Project Management Board has disbursed 49% of the total capital for 2025. According to the plan, by the end of November, the disbursement progress will reach 83% and strive to reach 98% by January 31, 2026.
For the Ham Thuan Nam Area Investment and Construction Project Management Board, as of mid-October, over 67.6 billion VND out of 128.46 billion VND had been disbursed, reaching 52.6% of the allocated capital plan. After capital adjustments, the unit will accelerate the implementation of projects with the determination to disburse over 80% by the end of November 2025.

During the meeting, representatives from relevant departments and units proposed several solutions to address obstacles and overcome shortcomings from the past. These solutions focused on areas such as: land compensation and clearance, approval of final project accounts, and detailed allocation of capital plans.
Concluding the meeting, Vice Chairman of the Provincial People's Committee Nguyen Minh acknowledged the positive progress in the disbursement of public investment funds by the regional investment and construction project management boards. He also requested that departments, agencies, and localities continue to seriously implement the directives of the Provincial People's Committee regarding this matter.

The Vice Chairman of the Provincial People's Committee noted that relevant parties need to proactively coordinate in reviewing each project, proposing solutions to obstacles, especially new requests and issues arising during implementation. At the same time, attention should be paid to providing human resources support to localities, promptly resolving difficulties in compensation, land clearance, support, and resettlement…
Source: https://baolamdong.vn/lam-dong-tap-trung-go-vuong-cho-cac-du-an-dau-tu-cong-nam-2025-396100.html






Comment (0)