
At the meeting, representatives of the Regional Construction Investment Project Management Boards reported on the progress of public investment projects in the area in the past time. At the same time, they proposed tasks for implementation in the remaining months of 2025.

According to the report, the Tuy Phong Area Construction Investment Project Management Board has currently disbursed more than 112/212.4 billion VND, reaching nearly 53% of the 2025 capital plan. In the coming time, the Board will urge construction units to focus on human resources, machinery and equipment to speed up progress and organize project acceptance when there is a volume of work.
It is expected that by the end of the year, the Regional Construction Investment Project Management Board will disburse over 95% of the capital plan and continue to strive to achieve even higher results by January 31, 2026.
For the Bac Binh Regional Construction Investment Project Management Board, the capital plan for 2025 is more than 181.3 billion VND, and at the time of reporting, the disbursement has reached approximately 56%. In the remaining months, the unit continues to coordinate with relevant parties to remove difficulties and obstacles of a number of projects to promote implementation progress. It is expected that by the end of the year, the disbursement will reach over 95% of the assigned capital plan.

As of October 20, 2025, the Ham Thuan Bac Construction Investment Project Management Board disbursed 49% of the total capital in 2025. According to the plan, by the end of November, the disbursement progress will reach 83% and strive to reach 98% by January 31, 2026.
As for the Ham Thuan Nam Area Construction Investment Project Management Board, as of mid-October, more than 67.6/128.46 billion VND had been disbursed, reaching 52.6% of the assigned capital plan. After adjusting the capital, the unit will accelerate the implementation of the projects with the determination to disburse more than 80% by the end of November 2025.

At the meeting, representatives of relevant departments, branches and units proposed a number of solutions to remove obstacles and overcome existing problems in the past time. In particular, focusing on tasks such as: Compensation and site clearance, approval of capital settlement for completed projects, detailed allocation of capital plans, etc.
Concluding the meeting, Vice Chairman of the Provincial People's Committee Nguyen Minh acknowledged the positive changes in the disbursement of public investment capital by the Regional Construction Investment Project Management Boards. At the same time, he requested departments, branches, units and localities to continue to strictly implement the instructions of the Provincial People's Committee on this work.

The Vice Chairman of the Provincial People's Committee noted that relevant parties need to proactively coordinate to review each project, propose solutions to obstacles, especially new recommendations and issues arising during the implementation process. At the same time, pay attention to and support human resources for localities, promptly resolve difficulties in compensation, site clearance, support, resettlement, etc.
Source: https://baolamdong.vn/lam-dong-tap-trung-go-vuong-cho-cac-du-an-dau-tu-cong-nam-2025-396100.html
Comment (0)